Pre-drilling
Contractor: Histon Global Ltd
-
Site Preparation
- Clearing & removing the soil (Status: 100% Completion)
- Spreading of heaps (Status: 95% Completion)
- Supply of chap sand (Status: 50% Completion)
-
Road Construction
- Spreading of stones (Status: 30% Completion)
-
Pipeline ROW
Ubima-1 Re-entry
- Workover
- Completions
- Testing
- Workover
-
Productions and evacuation
- Crude in storage tank at Ubima (bbls)
- Crude Evacuation - Crude Injection